Bhubaneshwar Thermal Power Project

Nhance designed and provided fabrication drawings of Coal Handling Plant for the 2x67.5MW TPP. One of the design challenges was in designing the 54m tall slender junction tower for wind speeds of 180kmph while maintaining the deflection criteria and optimizing the weight of the structure. This was a fast track project that was completed in under two and half months including approvals from the owner’s engineers Toshiba Power Systems Limited. Our work also involved design of crusher houses and screen houses. In addition to the design of CHP, nhance also provided fabrication drawings for the TG building structure.

  • Location : Anantapur, Odisha
  • Owner : Bhubaneshwar Power Private Limited
  • Architect & client : Bevconwayors Pvt Ltd